2025 Texas sessionsRegular and both called sessions have ended. This index covers House and Senate bills, not resolutions. Statuses come from official reports.

← Back to bills and search results

2025 · Regular session · House bill

HB2692

HB2692 puts the San Antonio River Authority's governing law into a single code chapter and changes some of its wording and procedures.

Read bill highlights ↓

Official caption: Relating to the San Antonio River Authority.

Became law without signatureSource-checked explanation published

Official report lists House author(s): Guillen. This does not identify sponsors or amendment drafters.

Report an error ↗

Bill explanation published · Version and amendment review scope is stated below · Individual amendment records may not be separately annotated.

Bill highlights

Selected points from the published explanation. Follow each point to its source-linked context; conditions and limits may matter.

Read the full explanation ↓

What does it do?

HB2692 puts the San Antonio River Authority’s governing law into a single code chapter and changes some of its wording and procedures. It concerns the existing authority in Bexar, Wilson, Karnes and Goliad counties, not a newly created district. The bill became law without the governor’s signature and took effect May 29, 2025. See the enrolled law, Chapter 8513 and act sections 2–3 and official history.

The law carries forward water supply, flood control, wastewater, pollution prevention, navigation, parks and related powers. It retains a 12-member elected board: six directors from Bexar County and two from each other county. Four-year terms, the transition election schedule, board training, public-comment and complaint procedures, and safeguards for affiliated nonprofits largely come from earlier law, including 2023 HB1535; they are not all new 2025 reforms.

The authority’s ordinary property-tax ceiling remains 2 cents per $100 of taxable value. Authorizing that tax requires both a districtwide majority and majorities in at least three counties, with hearings in each county. The money cannot fund the listed major construction or right-of-way acquisition costs or secure authority bonds. Separate pollution-control districts have their own hearing, election and tax rules; the ordinary 2-cent ceiling is not a blanket limit on those taxes. Revenue bonds still require eight directors’ approval, not a public election. These are powers to act under specified conditions, not a tax increase or bond issue imposed by HB2692 itself.

What changed along the way?

The text index contains five versions. The amendment index lists no floor amendments. Compared with the introduced bill, the House substitute revised drafting and references and narrowed the repeal list to the old governing act and specified provisions of seven later acts. Its operative text survived through enrollment. The House passed the bill 104–32, with two present but not voting; the Senate passed it 31–0.

Comparison with the authority’s consolidated law through 2023 reveals differences worth distinguishing from simple renumbering. Old section 21-b(a) limited subsidiary pollution-control districts to powers concerning waste treatment; new section 8513.0801 refers to any of the authority’s powers and purposes. Old section 3(j)(1) required two weekly newspaper notices for covered water-supply contracts; section 8513.0317 still requires publication but does not specify that frequency. Old section 3(a)(5) limited franchise suspension or forfeiture to discrimination unless the franchise provided otherwise; section 8513.0325 retains a district-court-order requirement unless otherwise provided, but omits that specified ground.

For covered construction and service contracts, section 8513.0318 retains bidding and two weekly notices, emergency exceptions and access to other lawful procurement methods. Its exemption is worded as a purchase contract, a procurement contract, or a contract described by Water Code 49.278; the earlier text tied the purchase/procurement exception to that Water Code provision. This does not establish that all other procurement laws cease to apply.

Section 8513.0209 states a 60-day annual limit on directors’ daily allowances, compared with 150 days in old section 11. But Water Code 49.060 as it stood before HB2692 already imposed a controlling annual compensation limit for authorities created by special law. It would be misleading to claim a simple 150-to-60-day pay cut. The new chapter also omits the old act’s 6-percent bond-interest wording and 15-percent fee for collecting delinquent taxes through suit, and changes a county tax-collection fee from 2 percent to not more than 2 percent. Those textual changes alone do not establish actual borrowing costs, collection charges or savings under other applicable law.

The law preserves existing water rights and the Guadalupe-Blanco River Authority’s priority where powers overlap. Its eminent-domain section expressly conditions that power on the authority having made the required filing by December 31, 2012; it is not an unconditional new grant. The next Sunset review is scheduled for 2035 and every 12th year thereafter. See sections 8513.0104–.0106, .0319, and subchapters F–H.

For the full amendment record, open the official amendment index.

Official bill versions

Compare the published text versions in the official text index. A change is not attributed to a specific amendment here without a verified record.

Who could benefit—and who could bear the costs?

Residents, water customers, property owners, contractors and the authority can find the governing provisions in one code chapter. That may make the law easier to use, but it does not itself guarantee lower bills, less flooding or faster projects. The subsidiary-district purpose wording and contract-notice changes matter when the authority considers future projects; taxpayers retain the applicable hearing and voting protections. The act does not itself create a subsidiary district or approve a particular project’s borrowing. See the final law, especially subchapters C and H.

The May 9, 2025 fiscal note anticipates no state fiscal implication and no fiscal implication for other local governments. It cannot determine the effect on this river authority because its future use of eminent domain, bonds, assessments, fees and taxes is unknown. The March 31 and April 17 notes reach the same result. This is not a finding of zero local cost or a quantified saving. The act makes no appropriation.

Official sources

Catalog report retrieved 2026-10-25. Check the official record for corrections or later changes.