2025 · Regular session · Senate bill

SB1150

SB1150 tightens the rules for extending the plugging deadline for older, long-inactive wells and adds testing reports, statewide reporting and enforcement provisions.

Read bill highlights ↓

Official caption: Relating to the plugging of and reporting on inactive wells subject to the jurisdiction of the Railroad Commission of Texas; authorizing an administrative penalty.

Signed by governorSource-checked explanation published

Official report lists Senate author(s): Middleton. This does not identify sponsors or amendment drafters.

Report an error ↗

Bill explanation published · Version and amendment review scope is stated below · Individual amendment records may not be separately annotated.

Bill highlights

Selected points from the published explanation. Follow each point to its source-linked context; conditions and limits may matter.

Read the full explanation ↓

What does it do?

SB1150 tightens the rules for extending the plugging deadline for older, long-inactive wells and adds testing reports, statewide reporting and enforcement provisions. Its main extension changes take effect September 1, 2027—not September 2025. Under existing law, “inactive” means an unplugged well with no reported production, disposal, injection or other permitted activity for more than 12 months. It is not necessarily an orphaned well with an absent operator. Final law, sections 1 and 5; Prior Natural Resources Code 89.002.

The ordinary extension route will no longer be enough when a well has been inactive more than 15 years and was completed more than 25 years before the extension request. The commission may still grant an extension through specified alternatives: an order based on a demonstrated record of returning wells to operation or financial hardship; an approved plan committing to plugging or production, injection or another operation by September 1, 2042; or an individual performance bond for at least the commission’s full plugging-cost calculation that covers the well’s lifetime despite operator changes. This is not an unconditional 2042 deadline or automatic extension for every well. The separate restriction where commission rules or orders already require plugging remains. Final law, section 89.023(b)–(c); Prior Natural Resources Code 89.023.

A hardship request requires an authorized representative’s signed attestation and a sworn financial statement certified by a certified public accountant. The commission may consider financial, investment, compliance and economic factors. For compliance plans it must consider the listed factors, including well age, inactivity, economic conditions, the operator’s inactive-well share and plans, compliance history, financial assurance, public or environmental hazards and good faith. A denied plan may be taken to a commission hearing. Record-of-recovery and hardship extensions under (c)(1) are not transferable; the act separately requires rules for joint written transfer affirmations of compliance, good faith and continued compliance. The commission sets an administrative penalty amount for violations. Final law, section 89.023(d)–(j).

The commission must report annually by December 1, with its first report due December 1, 2026. Required information includes well counts, ages and inactivity, extensions and financial assurance, plugging by operators versus the state, returns to operation, operator compliance and delinquency, unapproved or unrenewed organization reports and associated financial security, and the annual plugging-cost calculation. This annual report is numbered 89.049 in SB1150’s enrolled text. Final law, sections 2–3.

For each inactive well whose relevant completion report was filed at least 15 years earlier, its operator must submit an annual report documenting a successful fluid-level or hydraulic-pressure test conducted under commission rules. That clock is based on the completion-report filing date, not 15 years of inactivity. Rulemaking must consider public and environmental risk, well integrity and regional hazards such as corrosive or over-pressured formations and hydrogen sulfide. Final law, sections 89.050–89.051.

Signed June 20, 2025, the act generally took effect September 1, 2025, but the amendments to section 89.023 take effect September 1, 2027. Implementing rules must be adopted by December 31, 2026, and those rules must take effect September 1, 2027. These separate dates should not be collapsed into a claim that all new plugging restrictions began in 2025. Official history; Final law, sections 4–5.

What changed along the way?

The Senate substitute reorganized the introduced proposal and added express hardship and lifetime full-cost-bond alternatives, an administrative penalty and revised reporting and testing provisions. It changed the commission’s annual reporting date from September 1 to December 1 and delayed the main extension changes to 2027. The introduced proposal’s testing timetable depended on years of inactivity; that did not remain the final trigger. Introduced text; Senate substitute.

Middleton’s adopted April 22 Senate amendment moved the plan endpoint from 2040 to 2042, substituted joint written transfer affirmations and made the test report annual using completion-report age. The House committee substitute then removed hardship, returned the plan date to 2040, removed the delayed effective date and clarified the testing threshold to 15 years elapsed since the completion report was filed. Senate amendment; Engrossed text; House substitute.

Darby’s adopted May 22 House amendment restored hardship with the attestation, certified financial statement and consideration factors; restored the 2042 plan endpoint; expressly included injection or other operation; and restored the 2027 extension effective date while adding the rulemaking deadlines. It also changed the wording of who must consider compliance-plan factors. The Senate concurred May 26, and these provisions appear in the final law. Reynolds’s separate amendment, which would have added test-failure rates by inactivity and district and district-level average plugging-cost data to the report, failed and is not part of the act. Adopted Darby amendment; Failed Reynolds amendment; All amendment dispositions; Final law.

For the full amendment record, open the official amendment index.

Official bill versions

Compare the published text versions in the official text index. A change is not attributed to a specific amendment here without a verified record.

Who could benefit—and who could bear the costs?

The reporting, testing and extension limits can improve visibility into aging wells and their risks; operators face documentation, testing, bonding or plugging obligations as applicable. The hardship, recovery-history and plan routes preserve flexibility rather than requiring every older inactive well to close at once. Actual plugging, environmental gains and private compliance costs depend on implementation and individual wells; the act does not quantify those outcomes. Final law.

The final indexed fiscal note forecasts dedicated Oil and Gas Regulation and Cleanup Account costs of $6,036,855 in fiscal 2026, $4,882,756 in 2027 and $14,884,216 in 2028. It assumes seven additional full-time-equivalent positions in 2026–2027 and 86 from 2028, plus information-system work. Its $0 general-revenue-related headline does not mean zero cost: it assumes the dedicated account pays, with general revenue used if that account is insufficient. Penalty revenue cannot be determined; no local-government fiscal impact is anticipated. The bill itself makes no appropriation. May 25 as-passed fiscal note.

Earlier fiscal estimates differ because the proposal and implementation schedule changed. The final fiscal note also describes a September 1, 2026 reporting deadline, but enacted sections 2–3 require December 1 and the first report by December 1, 2026. This explanation follows the enacted text for legal duties and the fiscal note for its estimates. Versions and fiscal notes; May 25 as-passed fiscal note; Final law.